The complete mechanical and electrical refurbishment to an existing unused Grade II Victorian school building to create a new school for the French Education Property Trust was undertaken for this project, maintaining as many of the original features as possible.
A large and complex project, where Raytell became the main contractor half way through the project due to the previous main contractor going into receivership.
The Phase I works involved the following elements:
Electrical
Mains & Sub Mains Power
Internal & External Lighting CCTV
Fire Alarm Data/Voice
Access Control Intruder Alarm
Mechanical
Internal & External Public Health Pipework
Rainwater Pipework & Guttering
Hot & Cold Water Plant & Distribution
Air Conditioning
Supply & Extract Ventilation
Controls & BMS
Other
Builders Works
Lightning Protection
Phase II of the works, completed in Spring 2012 consisted of the installation of M & E works to additional classrooms, Library and outside toilet block