Barbican – Conservatory

  • thumb image
  • thumb image
  • thumb image
  • thumb image

Project Facts

  • Project completed on time and to budget.
  • All works were carried out whilst the Barbican Centre was open to the public

Key Details

  • Client Corporation of London
  • Electrical Contractor Raytell Electrical Co Limited
  • Contract Value £290K
  • Contract Duration 20 weeks

Works carried out:

  • The new emergency and secondary lighting including all containment to the Conservatory area and Canopy entrance.
  • The new installation of overhead lanterns to the Conservatory Mezz Party area, including all containment,.
  • The installation of new distribution boards and sub-mains including all containment to control all of the lighting distribution installed.
  • The installation of new lighting and emergency exit signage including controls to subways.

 